With reference to Table 11.11 on page 532 of the course textbook:

 Assuming that the cost of each activity is linearly distributed over its duration, create two budgets as follows:

  1. The first budget should assume an early-start schedule 
  2. The second budget should assume a late-start schedule 
  3. Explain why the two budgets are different 

Hint: Your budgets should be presented in the same formats as that of the examples on Tables 11.4 & 11.5, on pages 517 & 518 respectively. 

Do not submit your budgets as screenshots – rather submit in editable formats such as in Word or Excel